Progress March 2012 - Four Points by Sheraton Hotel & Tower:
Architectural and M&E works are in progress at various levels with most M&E equipments being installed. Sandakan Harbour Mall: The mall component is nearing completion and is in the midst of achieving the occupancy certificate. June 2010 - Hotel tower: Structural works on Level 10 are completed. Works are in progress at Level 11.
Retail podium: Structural works on Level 5 are completed. Works are in progress at Level 6.
Brickworks are in progress on Ground, First and Second floors. March 2010 -All three and four storey shop lot (Phase 2A / B) are completed and handed over to purchasers. Structural works in Phase 3 and 4 (Hotel and Mall), level 6 and 7 are in progress. December 2009 -Phase 3 & 4: Shopping mall substructure and ground structure works completed. Structural works for hotel tower Level 4 and retail podium Level 1 are progressing well. September
2009 -Phase 3 & 4: Shopping mall substructure and ground structure works are in progress. Structural works for hotel tower Level 3 are progressing well. June
2009 - 3- and 4-storey shop offices (40 units) in Phase 2A have been fully completed in early April 2009. Phase 2B of 3- and 4-storey shop offices (28 units) has also been completed in mid May 2009. Construction of the shopping mall, hotel and convention centre (Phase 3 and 4) commenced in early September 2008 - pilecap works, ground slab concreting and ground floor column works are progressing well. March
2009 - For the 3- and 4-storey shop
offices in Phase 2, the plastering of
external walls, door and window frame
fixtures completed. Roof installation and
internal plastering are currently in
progress. |